Fermentation plants Würselen

Project period

2009 until 2012

Client

AWA Entsorgung GmbH

Task and implementation

AWA Entsorgung GmbH operates a composting plant for biowaste in Würselen. Until it was rescheduled, pre-rotting took place in closed windrow composting with pressure ventilation. An open biofilter was used to clean the exhaust air. The main rotting as well as the fine compost processing and storage were carried out in a covered area. Our tasks were to increase the treatment capacity of 11,000 Mg/a and reduce odour emissions.  

For this purpose, we planned the expansion of the plant to include a dry fermentation system and also modernised the process control. The total capacity could thus be increased almost threefold. The new fermentation plant is based on dry fermentation in a partial flow process and consists of seven fermentation boxes. In five newly constructed rotting tunnels, the fermentation residues mixed with fresh biowaste are subjected to intensive rotting. The hall formerly used for intensive rotting is now used for post-rotting; the former area for post-rotting is used as a post-ripening area and storage. In a combined heat and power plant, the biogas produced during fermentation can be converted directly on site into electricity and heat.

Project data

  • Total capacity of up to 30,000 Mg/a  
  • 7 tunnel fermenters
  • 5 intensive rotting tunnels
  • Mobile core machines such as shredders, trommel screens, wheel loaders, transfer machines
  • Conveyor technology such as feed feeders, conveyor belts, magnetic separators
  • Biogas utilisation in the on-site combined heat and power plant
  • Underground percolate storage
  • Foil storage for the biogas

Services

  1. Basic evaluation
  2. Preliminary planning
  3. Design planning
  4. Coordination of the experts for building ground, odour and VAwS*
  5. Preparation for the awarding of contracts
  6. Participation in the awarding of contracts
  7. Accompaniment of the approval and works planning of the general contractor(s)**
  8. Site management

* Ordinance on Installations for Handling Substances Hazardous to Water
** General contractor